Achievements


  • Highest Generation achieved in Last one decade - 2789.062 MU
    Highest ever DC achieved 70.55 %
    Lowest annual SOC 0.689 ml/kwh
    Highest day Generation achieved on 25 th Dec 2020- 12.359 MU
    TDC Mines: Coal Production commenced from 10.12.2020, coal transportation started from PFPD from 19/03/2021
    Settlement Agreement signed with DEC for Project Closure for U#7
    Sanction for Rs.2650 Cr loan received from WBIDFC to retire high interest loan
    PPA, jointly signed between DPL and WBSEDCL and submitted to WBERC for Approval.
    Two part Tariff order for FY:19-20 issued by SERC in November 2020

Performance at a glance